PM FPX 5334 Assessment 2

What’s Included:

Ace your assessment in just 30 minutes with our proven distinction-winning guide.

Assessment Overview

Sample Paper

Optimizing Project Management: An In-Depth Analysis of NearlyFree.com’s Budget Challenges

Introduction

PM FPX 5334 Assessment 2 NearlyFree.com is already facing trouble with a project that has cost an original $25,000. The business is only 43% complete and has experienced significant flaws and is now in need of professional assistance in overseeing its project services. A review of a financial statement reveals a main discrepancy regarding the earned value, which has been considerably under-budgeted. The primary goal of NearlyFree.com’s project is to develop and implement an automated web-based training system for the new employees. The project is aimed at automating the New Employee Orientation (NEO) process, thereby reducing the workload and resource requirements.

Project Overview

The project scope at present defines a 92-day schedule with an approved budget of $22,300. This report gives a comprehensive analysis of the earned value method, evaluates project success, and provides required earned value calculations to enable an effective turnaround.

Understanding the Earned Value Technique

The Earned Value (EV) technique is a significant project management technique that tracks the project plan, work completed, and worth of work completed. The EV technique enables the project manager to ascertain whether the project is progressing as planned. Through actual and planned expenditure comparison, the technique is helpful in informing both time management and cost management. Control action is exercised relative to cost baseline, basing on essential calculations to yield efficient reporting of project progress.

Key Inputs in Earned Value Analysis

• Earned Value (EV): It calculates the amount of actual accomplishment of activities up to the date of analysis.

• Planned Value (PV): It calculates the planned spending of funds according to the project schedule up to the date of analysis.

• Actual Cost (AC): This is the actual amount spent up to the date of analysis.

Essential Calculations

Cost Variance (CV)

Cost variance represents the budget difference at the analysis moment and is calculated by the following formula:

[\text{Cost Variance (CV)} = \text{Earned Value (EV)} – \text{Actual Cost (AC)}]

Cost Performance Index (CPI)

This index represents the project’s budget difference in relation to its total size:

[\text{Cost Performance Index (CPI)} = \frac{\text{Earned Value (EV)}}{\text{Actual Cost (AC)}}]

Schedule Variance (SV)

Schedule variance is the project schedule variation at the analysis date and is calculated as follows: [

\text{Schedule Variance (SV)} = \text{Earned Value (EV)} – \text{Planned Value (PV)}]

Schedule Performance Index (SPI)

PM FPX 5334 Assessment 2 This metric provides information regarding the project performance against its planned schedule: [

\text{Schedule Performance Index (SPI)} = \frac{\text{Earned Value (EV)}}{\text{Planned Value (PV)}}]

Key Metrics and Current Performance

MetricValue
Budget Cost of Work Performed$12,373.95
Budget Cost of Work Scheduled$20,453.95
Actual Cost of Work Performed$16,373.95
Schedule Variance (SV)-$8,080.00
Cost Variance (CV)-$4,000.00
Schedule Performance Index (SPI)Cost Performance Index (CPI)0.600.76

Analysis of Schedule Variance (SV)

The schedule variance indicates that the project is behind schedule: [ Schedule Variance (SV) = Earned Value (EV) – Planned Value (PV) ] [ SV = $12,373.95 – $20,453.95 = -$8,080.00 ]

Cost Variance (CV) Insights

The cost variance reflects the monetary variances from the initial budgeting:

Cost Variance (CV) = Earned Value (EV) – Actual Cost (AC)

] [

CV = $12,373.95 – $16,373.95 = -$4,000.00 ]

Performance Indices Interpretation

• Schedule Performance Index (SPI): With a reading of 0.60, the SPI reflects that the project is critically behind schedule because an SPI reading below 1 reflects delays.

• Cost Performance Index (CPI): The value of 0.76 for CPI means that for each dollar spent, less value is being obtained than expected, indicating potential cost overruns.

Budget at Completion (BAC) and Estimate at Completion (EAC)

The Budget at Completion (BAC) for NearlyFree.com is $22,300. However the Estimate at Completion (EAC), or projected total cost of the project to date based on existing performance, is as given below: [ \\\\text{Estimate at Completion (EAC)} = \\\\text{Actual Cost (AC)} + \\\\frac{(\\\\text{Budget at Completion (BAC)} – \\\\text{Earned Value (EV)})}{\\\\text{Cost Performance Index (CPI)}} ] [ \\\\text{EAC} = \\\\$16,373.95 + \\\\frac{(\\\\$22,300 – \\\\$12,373.95)}{0.76} = \\\\$29,434.54 ]

Strategic Budget Turnaround

Applying Earned Value Analysis (EVA) is required in order to monitor project progress, estimate completion duration, and identify budget and schedule variances. NearlyFree.com’s initial EVA for the NEO project states that it is over 50% behind schedule, with a total budget overrun. A better EVA would have provided a clearer timeline and budget.

Conclusion

PM FPX 5334 Assessment 2 To ensure project success, NearlyFree.com will need to extend the time horizon and revisit the budget, increasing the Estimate at Completion to $29,434.54 from $22,300. Such adjustments are necessary because exceeding the original budget or timeline can jeopardize stakeholder confidence, affect stock market performance adversely, and damage the firm’s financial position. A correct project schedule would prevent the risk of further cost overruns and ensure successful project completion.

References

Cullen, S. (2nd August 2016). Earned value analysis. WBDG. WBDG%20is,budget%20as%20the%20 project%20 proceeds).https://www.ncbi.nlm.nih.gov/pmc/articles/PMC2870361/

Haughey, D. (26th July 2020). What is earned value? ProjectSmart. ProjectSmart.

Peng, B. (10th April 2018). The earned value method. Project Engineer. Project Engineer.https://www.ahrq.gov

PM FPX 5334 Assessment 2 Bausch + Lomb Project

Usmani, F. (18th August 2020). Planned value (pv), earned value (ev) & actual cost (ac) in project cost management. PM Study Circle. PM Study Circle

References (APA 7 Format)

Step-by-Step Guide

Frequently Asked Questions (FAQs)

Author

Integrity Note

Use this example for learning and structure only. Do not submit as your own work.
We are an independent resource and are not affiliated with Capella University.

Table of Contents

Nursing assignment help
About us

Why Students Trust Us With Their Work

Our expertise is laser-focused on RN to BSN and RN to MSN pathways, offering tailored support that addresses the unique challenges and opportunities these programs present.

We understand the aspirations of students striving for excellence in nursing. Our mission is to bridge the gap between your current RN status and your goals of obtaining a BSN or MSN, propelling you towards a successful nursing career.

Write research papers for nurse

“I had a research paper written by the service. They delivered an excellent piece with thorough analysis and accurate referencing. Impressive work!”

Order ID # 00981

BSN - Capella University

Our Top Writers this Month

mew-ethan-c

Ethan Collins

⭐⭐⭐⭐⭐

Experience : 10+ Years in Nursing.
Specialization : BSN, MSN

mew-sophia-w

Sophia Walker

⭐⭐⭐⭐⭐

Experience : 10+ Years in Nursing.
Specialization : MSN, DNP

mew-noah-p

Noah Peterson

⭐⭐⭐⭐⭐

Experience : 10+ Years in Nursing.
Specialization : DNP, PSY

How it Works

Our services are exclusively designed for RNs advancing towards BSN and MSN degrees.

Tailored Academic Support

Specialized Guidance for RN to BSN & RN to MSN

Comprehensive Resource Hub

Your One-Stop Resource for Nursing Advancement

Career-Focused Mentorship

Beyond Academics Your Bridge to Nursing Leadership

Personalized Learning Experience

Customized Support for Every Step of Your Journey

Scroll to Top

Get your NURS Assessment
in just 24 hours!