Optimizing Project Management with Earned Value Analysis: A Case Study of NearlyFree.com

Introduction

PM FPX 5333 Assessment 2 NearlyFree.com is currently dealing with a project that has exceeded its initial budget of $25,000. As the project is 43% complete, the company has learned its mistakes and has requested our project management services, An intense review of the annual accounts of the project indicates that the earned price is within the budget. The project is attempting to develop and disseminate an automated online training system for new hires, therefore lowering the fee and minimizing the staff resources needed for new employee orientation (NEO) training.

The project scope determines the 92-day program with a budget approved at $ 22,300. The report will explore the earned price technology (if any), assess the project’s current status and perform the earned price calculation necessary to facilitate an effective turnaround strategy.

Understanding the Earned Value Technique

Acquired price (EV) technology is a vital way of monitoring the correlation between a project plan within a project management in project management, actual progress and value of the work. The technology can be utilized to decide whether the project ought to have used how much time should have been used based on the work done by assessing the project. Control on project is undertaken against the basis of cost through applying the earned value, which occurs in terms of calculating and presenting a set of key performance indicators based on the actual progress.

Key Inputs in Earned Value Analysis

• Earned Value (EV): The current actual progress of the task up to the analysis date.

• Planned Value (PV): The forecasted expenditure of funds up to the date of analysis based on the calculation from the project schedule.

• Actual Cost (AC): The actual amount of money actually expended during the time period being analyzed.

Essential Calculations in Earned Value Management

In understanding how well or badly the project is performing, some very important calculations can be performed:

Cost Variance (CV)

Cost Variance (CV) specifies by how much the project is ahead or behind schedule at any point in time. It can be calculated as:

[ Cost Variance (CV) = Earned Value (EV) – Actual Cost (AC) ]

For the project:

[ CV = $12,373.95 – $16,373.95 = -$4,000.00 ]

A cost variance of -$4,000 indicates that the project is running behind budget, while the optimum variance will be higher or zero.

Schedule Variance (SV)

Schedule Variance (SV) checks whether a project is ahead or behind time. The formula is:

[ Schedule Variance (SV) = Earned Value (EV) – Planned Value (PV) ]

For this project:

[ SV = $12,373.95 – $20,453.95 = -$8,080.00 ]

This negative schedule variance indicates that the project is way behind schedule.

Performance Indices

• PM FPX 5333 Assessment 2 Schedule Performance Index (SPI) measures the effectiveness of the project in relation to its planned completion:

[ SPI = Earned Value (EV) / Planned Value (PV) ]

For this project:

[ SPI = $12,373.95 / $20,453.95 = 0.60 ]

An SPI of 0.60 indicates that there is a lag in the progress of the project, as any value below 1 indicates the project is behind.

• Cost Performance Index (CPI) gauges the financial performance of the project:

[ CPI = EV / AC ]

For this project:

[ CPI = $12,373.95 / $16,373.95 = 0.76 ]

A CPI of 0.76 suggests that the project is facing financial issues, since a CPI of less than 1 indicates inefficiency in cost control.

Project Budget and Future Projections

Budget at Completion (BAC)

Budget at Completion (BAC) refers to the total budget spent on the project. For NearlyFree.com, BAC is $22,300 initially.

Estimate at Completion (EAC)

Estimate at Completion (EAC) predicts the total cost of the project using its history. The EAC formula is as follows:

[ EAC = Actual Cost (AC) + (Budget at Completion (BAC) – Earned Value (EV)) / Cost Performance Index (CPI) ]

For this project:

[ EAC = $16,373.95 + ( $22,300 – $12,373.95 ) / 0.76 ]

[ EAC = $16,373.95 + $13,060.59 ]

[ EAC = $29,434.54 ]

Recommended Budget Turnaround Strategy

PM FPX 5333 Assessment 2 Earned Value Analysis (EVA) is a widely used technique for evaluating the progress of a project, estimating its completion time and final cost, and quantifying schedule and budget variances. Through the measurement of planned work and actual performance, EVA determines if cost, schedule, and work completed are in line with project expectations.

The recent EVA indicates that NearlyFree.com’s NEO project is over 50% behind schedule, and there are enormous budget overruns. A more planned EVA would have expected better budget needs and delivery times. The revised EAC indicates an increase in the project budget, from the original $22,300 to a new estimate of $29,434.54, which is a huge increase of over $7,000.

To offset these problems, it is recommended NearlyFree.com postpone the project schedule. This adjustment would provide ample time to complete the project, possibly improving earned value and decreasing incomplete work percentage.

Conclusion

Scheduling and budget shifts are critical in ensuring a successful project. Cost overruns have the potential to destroy stakeholder confidence, which might influence the performance of the company in the market and financing for future ventures. With the help of a more accurate project schedule and by performing the Earned Value Technique effectively, NearlyFree.com is able to handle its current challenges and improve general project management practices.

References

Peng, B. (2018, April 10). The earned value method. Retrieved from Project Engineerhttps://www.nibusinessinfo.co.uk

Usmani, F. (August 18, 2020). Planned value (PV), earned value (EV), & actual cost (AC) in project cost management. Retrieved from PM Study Circle

Haughey, D. (July 26, 2020). What is earned value? Retrieved from Project Smart

PM FPX 5333 Assessment 2 Earned Value Analysis Report 

Cullen, S. (2016, August 2). Earned value analysis. Retrieved from WBDG%20is,budget%20as%20the%20 project%20 proceeds.https://link.springer.com/

References (APA 7 Format)

Step-by-Step Guide

Frequently Asked Questions (FAQs)

Author

Integrity Note

Use this example for learning and structure only. Do not submit as your own work.
We are an independent resource and are not affiliated with Capella University.

Table of Contents

Nursing assignment help
About us

Why Students Trust Us With Their Work

Our expertise is laser-focused on RN to BSN and RN to MSN pathways, offering tailored support that addresses the unique challenges and opportunities these programs present.

We understand the aspirations of students striving for excellence in nursing. Our mission is to bridge the gap between your current RN status and your goals of obtaining a BSN or MSN, propelling you towards a successful nursing career.

Write research papers for nurse

“I had a research paper written by the service. They delivered an excellent piece with thorough analysis and accurate referencing. Impressive work!”

Order ID # 00981

BSN - Capella University

Our Top Writers this Month

mew-ethan-c

Ethan Collins

⭐⭐⭐⭐⭐

Experience : 10+ Years in Nursing.
Specialization : BSN, MSN

mew-sophia-w

Sophia Walker

⭐⭐⭐⭐⭐

Experience : 10+ Years in Nursing.
Specialization : MSN, DNP

mew-noah-p

Noah Peterson

⭐⭐⭐⭐⭐

Experience : 10+ Years in Nursing.
Specialization : DNP, PSY

How it Works

Our services are exclusively designed for RNs advancing towards BSN and MSN degrees.

Tailored Academic Support

Specialized Guidance for RN to BSN & RN to MSN

Comprehensive Resource Hub

Your One-Stop Resource for Nursing Advancement

Career-Focused Mentorship

Beyond Academics Your Bridge to Nursing Leadership

Personalized Learning Experience

Customized Support for Every Step of Your Journey

Scroll to Top

Get your NURS Assessment
in just 24 hours!