Project Scope Statement
Executive Summary
PM FPX 5332 Assessment 1 Cosmo Inc. is a prominent technology firm, particularly in fitness and nutrition education. Currently holding a market share of 33%, the firm is facing increasing competition, which calls for an in-depth marketing analysis. Based on the findings, CEO Harold Living has proposed a new marketing strategy to guarantee competitiveness. The project will involve the launch of a new technology product and a complementary strategic marketing campaign, with an implementation budget of $150,000 over a duration of 10 weeks. Target market involves individuals aged 25 to 50 with an annual salary of $75,000 and more. The project will be funded and managed by Harold Living, both CEO and President.
The overall goal of the Tech Lifestyle project is to expand market share and position Cosmo Inc. in a leading position in wearable technology. The project aims to achieve a 20% increase in market share and a 15% rise in the customers’ base among the target group identified. To better support customers in sync with the new offerings, the project shall introduce tools and systems to better support customers. In order to compete effectively with new technology companies, the project will undergo 10 weeks of preparation followed by a 6-month marketing campaign.
PM FPX 5332 Assessment 1 New Marketing Strategy
Due to the magnitude of the project, multiple departments will collaborate with each other to form specialty sub-teams that will work on specific tasks to ensure deadlines are met. The overall goal will be to accommodate existing customers as well as new potential customers.
Note: In case of conflict between the Project Scope Statement and the Project Charter, the Project Scope Statement shall be used as the ultimate document.
Business Objectives
Product Description (Solution)
Under the guidance of Mr. Living, the Life Style Tech program has been designed as a prolonged 6-month campaign with a focus on expanding Cosmo Inc.’s customer base.PM FPX 5332 Assessment 1 Under the guidance of Mr. Living, the Life Style Tech program has been designed as a prolonged 6-month campaign with a focus on expanding Cosmo Inc.’s customer base.
The major focus is placed on college-educated consumers in the 20 to 25 age group and with an annual income of $75,000 and more residing in cities with over 500,000 inhabitants. These individuals are characterized by their technologically oriented tendencies and high usage of cloud and mobile technology. Cosmo Inc. targets, in the long run, to get a higher share of the market from 33% to a minimum of 44%. The Life Style Tech program will facilitate this growth, allowing the company to compete in the market more effectively.
Project sponsor would be Mr. Living, under close monitoring from a project management team made up of marketing director, IT director, CFO, and customer service director.
Project Description
Project Scope
Deliverables:
• PM FPX 5332 Assessment 1 Research: Research will be carried out by the IT department based on both available data and fresh demographic data. The research will inform the integration and installation of the new technology. A pilot run will also be done to identify and fix any potential flaws prior to launching the product.
• Marketing: Demographic studies and competitor analysis will be done by the marketing team on tech-savvy individuals in the age group of 25 to 50. The new technology with improved features will be marketed using a six-month marketing campaign.
• Reporting: Data that can be acquired through the research will guide departmental strategies. For instance, customer service satisfaction levels can be used to aid marketing in gearing campaigns. Periodic reports and check-ins will have the finance department maintain budget compliance.
• Implementation: Sub-teams will convene once research and reporting are completed to seal product design, review marketing status, and examine the budget. The final product will be implemented with ongoing monitoring of progress.
Exclusions:
Project scope excludes phase and implementation detailed specifics, which will be covered as the project proceeds.
Dependencies (External and Internal):
• External: Success depends on factors beyond, such as the validity of the survey and interests of the target market.
• Internal: Success depends heavily on communication. Regular meetings and briefings will be crucial in facilitating cooperation and monitoring progress, with careful control of finances and timetables.
Assumptions:
The findings of the demographic analysis are assumed to hold true and are taken into account, assuming the project could be executed in time and as stipulated within budget.
Constraints:
Technology integration and time management constitute significant constraints where the level of complexity associated with the new technology has the tendency to induce delay.
Project Milestones
| Milestone | Target Date |
| Project Start | 10/19/2021 |
| Strategy | 10/20/2021 |
| Timeline, Reporting, Data Analysis | 10/22/2021 |
| Finance/Budget | 10/24/2021 |
| Development and Ideas/Marketing/IT | 10/27/2021 |
| Initial Implementation Draft Review | 11/01/2021 |
| Review/Ready for Implementation | 12/08/2021 |
| Final Review | 12/20/2021 |
| Project Completion and Implementation | 12/31/2021 |
Project Approach
Change Management:
Marketing, IT, finance, and customer service directors will provide periodic status reports in meetings to ensure consistent progress during the project.
Communication Management:
Bi-weekly meetings will be held within the first two weeks to coordinate all team members, and subsequently weekly meetings will be held with an emphasis on discussion, updates, and reporting.
Quality Management:
Quality assurance is paramount, with rigorous testing of the technology before the live launch. Test results will be presented at team meetings for review and discussion.
Resource Management:
Department directors will oversee resources within their own departments, ensuring the tools required are in place to ensure project success.
Critical Success Factors
Project success relies on effective communication, timely reporting, and extensive documentation.
Risk Management
Risks are inherent from project inception but can be controlled with clear-cut objectives, well-planned execution, and effective teamwork.
Project Organization
| Role | Name | Job Title | Responsibilities | Contact Information |
| Project Sponsor | Harold Living | CEO/President | Set goals and approve final plans | 111-1111 |
| Project Manager | Naureen Durrani | Program Manager | Oversee project progress and report to CEO | 111-2222 |
| Marketing Director | Elon Musk | Marketing Director | Conduct surveys and launch marketing campaign | 111-7777 |
| CFO | Jeff Bezos | CFO | Ensure budget compliance | 111-0000 |
| IT Director | John Apple | IT Director | Oversee new technology integration | 111-0101 |
| Customer Service Director | Tom Hiddleston | Customer Service Director | Prepare team for the product launch and provide tools | 111-9999 |
Authorizations
Project Sponsor: Harold Living
Project Manager: Naureen Durrani
Key Stakeholders: Elon Musk, Jeff Bezos, John Apple, Tom Hiddleston
Project Scope Statement Approval
The undersigned agree to the purpose and content of this document:
| Name | Role | Signature | Date |
| Harold Living | Project Sponsor | 10/16/2021 | |
| Naureen Durrani | Project Manager | 10/16/2021 | |
| Elon Musk | Marketing Director | 10/16/2021 | |
| Jeff Bezos | CFO | 10/16/2021 | |
| John Apple | IT Director | 10/16/2021 | |
| Tom Hiddleston | Customer Service Director | 10/16/2021 |