Part 1: Sprint Plan
Sprint Goal
PM FPX 4080 Assessment 5 The overall objective for this sprint is to raise customer retention by 20% by developing a sophisticated thermostat system that is controllable via a mobile app. In the past, CapraTek’s Alfred product line has not met profit, revenue-generating, and customer interest expectations mainly because of the incompatibility with mobile apps. During team discussions, there was an agreement that delivering a product that is better than what competitors can offer is essential. This objective is a primary driver for the team to complete the sprint backlog as well as ensure customer satisfaction.
For this objective to be attained, the project team must complete backlog tasks that are specially crafted to address customer retention issues. Some of the key tasks for this sprint are the development of an iOS mobile app to control the Alfred thermostat system, software development to ensure Wi-Fi support for the app, and coding of thermostat functions for user convenience. This feature will enable customers to adjust thermostat temperatures, monitor usage habits, and receive energy efficiency notifications. These goals not only guide the project team but also provide stakeholders with a clear understanding of the project vision.
Sprint Tasks
the tasks that are critical and putting them on the backlog, the following have been planned to be done within the first sprint:
| ID # | Task Description | Estimations | Priority Level | Start Date | End Date | Duration (Hours) | Status |
| 100-013 | Set security on iOS with password protection | System configuration (32 hrs) | High | 02/14/2022 | 03/11/2022 | 160 | Started |
| Secure key generation (32 hrs) | |||||||
| Input dedicated email inbox (32 hrs) | |||||||
| Secure key storage in module (32 hrs) | |||||||
| 100-001 | Create dashboard interface for thermostat settings | Database implementation (30 hrs) | High | 02/14/2022 | 02/25/2022 | 80 | Complete |
| Middleware development (25 hrs) | |||||||
| 100-002 | Create changeable interfaces and dashboard preferences | Embellish additional database interfaces (50 hrs) | High | 02/28/2022 | 03/18/2022 | 160 | In Progress |
| 100-009 | Create alerts for notification and energy efficiency purposes | Apply backend software to thermostat settings (24 hrs) | High | 03/01/2022 | 03/16/2022 | 96 | Not Started |
Roles and Responsibilities
During the project preparation session, the Smart Home Technologies Project Manager, Rachel Davis, was assigned the role of Scrum Master, and Darren Stokes, a CapraTek developer, was assigned the role of Product Owner. Rachel, with her expertise in Agile processes, will guide stakeholder interaction and a smooth process of implementation. Darren, being based on existing Alfred products, has first-hand information on the needs of the customers and will prioritize activities in terms of these, preventing any wastage of development time. The rest of the team members will belong to the Scrum team and collaborate synergistically to perform the activities listed in the project backlog.
PM FPX 4080 Assessment 5 Rachel’s responsibilities include monitoring team performance, conducting daily stand-up meetings, resolving issues, ensuring Scrum practice adherence, and assisting Darren with the backlog. Darren, being the Product Owner, is responsible for keeping the backlog up to date, prioritizing, identifying market needs, managing development phases, and assessing progress after every sprint. Both roles are essential in enabling stakeholders’ walkthrough of the Agile process and ensuring the successful execution of the project.
Sprint Burndown Chart
The following burndown chart shows the progress over the course of the 22-day sprint:
[Insert Burndown Chart Here]
Part 2: Updated Burndown Chart
“Done” Definition
At the end of every sprint, the product will need to be inspected to confirm that it has been completed to the completion criteria. For the current sprint, the Alfred thermostat will possess an iOS password-protected security system, a functional dashboard interface for controlling the thermostat, customizable dashboard preferences with trend drawings, and customer notifications on energy-efficient controls. In order to ensure completion, functionality testing, code reviews, static code analysis, unit testing, and performance testing shall be executed, along with corrective actions where necessary. After these quality check work are completed, the sprint is counted as done so that the team can move on.
PM FPX 4080 Assessment 5 The stand-up meetings daily are significant to talk about the problems, track progress, and give recommendations for the day-to-day mobile app development. The team must consent to the completion of the sprint; otherwise, the sprint cannot be seen as completed. According to the Agile Alliance, “Failure to meet these criteria at the end of the sprint normally implies that the work should not be counted toward that sprint’s velocity” (Definition, 2021).
In order to avoid incomplete sprint tasks, the team should ensure all the requirements are met and the needs of the customer are comprehensively addressed. This involves deciding if the new product features contribute to the target of enhancing customer retention by 20%. By applying checklists and establishing precise agreements, the team can automate pre-implementation activities, reduce rework, and reduce misunderstandings or disputes between team members and customers (Definition, 2021).
Below is the revised burndown chart, including team member sickness and necessary training. Even with a one-day delay, the team still has another day remaining, and this reassures the stakeholders that the problems have been addressed.
References
Capella University. (n.d.). Sprint Planning Meeting. Capella Media. Retrieved February 8, 2022, from https://www.agilealliance.org
PM FPX 4080 Assessment 5 The Sprint
Definition of done. Agile Alliance. (2021, March 3). Retrieved February 8, 2022, from https://www.agilealliance.org/glossary/definition